Keeping Production Running with an Effective Spare Parts Strategy

It's through experience that most sites learn which parts would stop production if they failed. Not a lot of sites know, however, how long production would then stay halted while a replacement is found and fitted, which is the figure a spare parts strategy is built around.

Working that out means putting two figures against every critical component; the first is how long the line can be down before the cost becomes a problem, and the second is how long it would realistically take to get a replacement fitted and running. Wherever the second runs past the first, there is a gap, and those gaps are what a spares strategy exists to close.

In this post, we cover how to arrive at both figures, why the recovery figure tends to be underestimated, and how holding the right spares can close the gaps that remain.

What is a spare parts strategy?

A spare parts strategy in automation is a plan that ensures the right replacement components are available when machinery fails. It is a data-driven approach that matches spare parts stock levels to the operational risk they carry.

Most strategies begin by ranking parts by criticality, and the two methods most commonly used for this are:

  • ABC analysis, which groups parts by their consumption value, with A covering the highest-value items and C the lowest.
  • XYZ analysis, which groups parts by how predictable their demand is, with X covering steady usage and Z the most unpredictable.

Those rankings show which parts matter most for a site and how often they are needed. To complete the strategy, a site also needs to know how long a line would stay down if one of those parts failed, which comes down to two figures for each critical part, one set by the line and the other by the part itself.

The two figures behind any spares strategy

Tolerable downtime and realistic recovery time are the two figures that show how exposed each line is to failure, and which spares a site should prioritise. Both are best worked out in advance, before any machinery fails, because neither can be estimated accurately during a breakdown.

Tolerable downtime

Every line can absorb a certain amount of stoppage without consequence, cushioned by buffer stock or slack in the schedule. Once that cushion runs out, costs start to become problematic.

The tolerance varies a lot between lines, which is why a single site-wide figure is of little use. A line with finished goods built up behind it can keep customers supplied through a stoppage, but a continuous process with nothing downstream stops delivering as soon as it stops running.

Realistic recovery time

The second figure is how long a line would stay down if a given part needed replacing, covering the diagnosis of the fault, getting the replacement on site, fitting it and restoring operations.

Most estimates take a supplier’s quoted lead time as the whole answer, leaving out the crucial steps before the order is placed and after the part arrives.

On a part that has never needed replacement, that figure is always an estimate, however carefully it is put together, but sending the part number to a reliable supplier ahead of time replaces the assumption with a real figure.

Once each result is set against the tolerable downtime for its line, the comparison shows which spares to hold first, with the parts whose recovery time runs past that tolerance at the top of the list.

Closing the gaps with a spare parts availability strategy

A spare parts availability strategy closes each gap by bringing a part’s recovery time back within what its line can absorb, which comes down to holding the right spares and working with a supplier who can get the rest on site quickly.

  1. Hold it

    Holding a spare on site is the most certain way to close a gap, since a part already on the shelf removes the sourcing stage from recovery altogether. It is the right answer for the parts at the top of the list, and the aim from there is to extend that cover down the list to every part a line depends on.

    The first parts to stock are often called insurance spares, meaning parts with long lead times, parts available from a single source and parts whose failure would stop production outright. They tend to be needed rarely, which makes them easy to leave off the shelf, though they are the ones a line can least afford to wait for.

    On sites running several lines or locations, spares can be held in a central store, where one spare covers more machines, or at each site, where it reaches the line faster, and many operations use a mix of both. Either way, stock needs keeping topped up so that a part is still on the shelf after one has been used, which is what minimum and maximum levels set from past usage are for, with a replacement ordered as soon as stock drops to its reorder point.

    Parts used across several lines are also well suited to buying in larger quantities, since a single order covers spares for every line that relies on them. Holding stock does tie up capital, though it is a far smaller cost than a stoppage on a line with nothing to absorb it.

  2. Find a supplier you can rely on

    A supplier who already knows a site’s equipment moves faster than one starting from scratch. With the critical parts list in hand, they can confirm what they hold and how quickly parts can be sourced, which turns the recovery figure from an estimate into a known quantity. Working with one supplier who covers many manufacturers cuts down on separate enquiries for each brand on site.

    Communication counts for as much as stock here, since a supplier who replies quickly, gives an honest lead time and is upfront about which parts are held and which need sourcing makes it easier to plan ahead and shorten stoppages.

    This applies to older equipment as much as current lines, since parts that have left production are often still available as new surplus, refurbished or used stock, across a wide range of manufacturers.

Planning ahead of the next breakdown

A machine failure is rarely predictable down to the day, so the control a site has lies in how quickly it recovers.

Keeping that recovery short means knowing which parts each line depends on and holding spares for as many of them as possible, starting with those that would keep a line down the longest.

With over 350,000 parts across nearly 1,000 manufacturers, including obsolete and hard-to-find stock, NRwell can source the spares your site needs. For more on finding a reliable partner, read our guide to choosing an industrial automation parts supplier, or get in touch with the NRwell team to talk through what we can hold for you.

Frequently asked questions

How do I estimate recovery time for a part we have never replaced?

Ask your supplier for a lead time on the part number, then add your own diagnosis, fitting and restart time. Checking this before failure gives a far more reliable figure.

Should spares be held for equipment due to be replaced?

Yes, in most cases, since a replacement project may be delayed and a line that is still running still needs parts.

Who should own the critical spares list?

Engineering and procurement teams should work together, since one knows the consequences of a failure and the other holds the lead times and supplier terms.

What are insurance spares?

Parts held on site because their failure would be costly, even though they are rarely needed, such as long-lead-time or single-source components.